AEL&P has completed another avalanche diversion structure on the Snettisham transmission line. This structure protects tower 4/5, and is the second diversion structure completed. The first diverter, on tower 4/6, was finished in 2009.
Photos: Snettisham gains protection 102412 NEWS 1 Capital City Weekly AEL&P has completed another avalanche diversion structure on the Snettisham transmission line. This structure protects tower 4/5, and is the second diversion structure completed. The first diverter, on tower 4/6, was finished in 2009.


Click Thumbnails to View
Wednesday, October 24, 2012

Story last updated at 10/24/2012 - 5:54 pm

Photos: Snettisham gains protection

AEL&P has completed another avalanche diversion structure on the Snettisham transmission line. This structure protects tower 4/5, and is the second diversion structure completed. The first diverter, on tower 4/6, was finished in 2009.

"These diversion structures are huge steel "wedges" constructed uphill of the transmission tower," said Eric Eriksen, vice-president of Transmission and Distribution. "If an avalanche comes toward the tower, these structures are designed to split the avalanche and divert it around the tower."

AEL&P has focused its avalanche protection efforts in the area of mile 3 and mile 4 of the Snettisham transmission line. The towers in this area are the ones that were damaged in the avalanches of 2008 and 2009.

In addition to completing the protective structure at tower 4/5 this season, crews were also able to prepare the site and install foundations for a diversion structure at tower 4/4. This will allow for completion of that structure in a future field season and at a lower cost than having to mobilize crews to do foundation work a second time.

The cost for constructing a diversion structure is roughly $2.2 million each. AEL&P received a grant of $2 million from the State of Alaska's Renewable Energy Fund to assist in the cost of constructing the diverters. "While all our costs are recovered through electric rates", explained Eriksen, "with the grant from the State, we were able to build these structures through our normal capital budgeting process."

In addition to building protective structures at specific towers, AEL&P also performs active avalanche control on the Snettisham line. An avalanche specialist on AEL&P's staff monitors weather and snow conditions in the area on a daily basis, and performs controlled releases of the snowpack as necessary to prevent the buildup of larger potential avalanches.